Name of scheme:                     Establishment of Sindhi language 

                                                        Authority at Hyderabad (ADP 353)

 

Date of approval                                         (29-04-1993)

 

Original Cost                                               12.209 Million

 

Date of Revised PC-I                                    (26-02-2003)

 

Revised Cost                                                22.738 Million

 

Expenditure up to end of last                          14.209 Million

Five Year June,2004  

 

Allocation 2004-05                                         2.000 Million

 

Revised allocation 2004-05                              2.000 Million

 

Releases up to month under report                    1.000 Million

 

Expenditure up to end of                                 1.000 Million

month under report                       

 

Expenditure as % age of allocation (CFY)              (100 %)

 

Expenditure as % age of Releases (CFY)               (100 %)

 

Physical progress in CFY up to reporting month        (54 %)

 

REMARKS  

 

As per report of the Chairman Sindhi language Authority, Hyderabad, work as per scheme is in progress. The funds allocated in the CFY as per PC-I would be fully utilized by the Authority.

 

 

Name of scheme:               Institute of Crafts Glazed and Pottery

                                                             Laboratory at Sindh Provincial

                                                           Museum,Hyderabad (ADP # 354)

Date of approval                                       (29-08-1994)

 

Original Cost                                             10.000 Million

 

Date of Revised PC-I                                 (11-01-2003)

 

Period                                                      (3 Years)

 

Revised Cost                                            20.351 Million

 

Expenditure up to end of last                       12.000 Million

Five Year June,2004            

 

Allocation 2004-05                                      2.000 Million

 

Revised allocation 2004-05                           2.000 Million

 

Releases up to month under report                        -

 

Expenditure up to end of month under report           -

 

Expenditure as % age of allocation (CFY)             (75 %)

 

Expenditure as % age of Releases (CFY)              (100 %)

 

Physical progress in CFY up to reporting month     (59 %)

 

 

REMARKS

 

Work of external development was awarded to the contractors after seeking technical sanction of the Chief Engineer (Buildings) & Chairman Interim Committee for Development works of C&TD. The Building Department was requested to carry on the civil works through its XEN at Hyderabad. Due to the technical hindrances and contractors obligations, funds were transferred to fast going schemes.

 

 

Name of scheme:                Establishment of Folk Crafts Museum

                                                              at Sehwan (ADP No.356)

 

Date of approval                                      (28-06-1993)

 

Original Cost                                            14.100 Million

 

Date of Revised PC-I                                 (03-09-2002)

 

Period                                                       (3 Years)

 

Revised Cost                                            28.617 Million

 

Expenditure up to end of last                       14.100 Million

Five Year June,2004            

 

Allocation 2004-05                                      2.500 Million

 

Revised allocation 2004-05                           2.500 Million

 

Releases up to month under report                 2.500 Million

 

Expenditure up to end of                    2.500 Million (Committed)

month under report                      

 

Expenditure as % age of allocation (CFY)            (50 %)

 

Expenditure as % age of Releases (CFY)             (100 %)

 

Physical progress in CFY up to reporting month     (55 %)

 

 

REMARKS

 

The civil works executed by the A.D, itself have been transferred to District Government to avoid un-necessary delay in the execution. All assistance including clearance of drawing have already been done.

 

Name of scheme:                                  Cultural Complex at Rani Kot

                                                                        Dadu (ADP No. 357)

 

Date of approval                                         (03-10-2003)

 

Period                                                         (4 Years)

 

Original Cost                                               38.827 Million

 

Expenditure up to end of last                          4.000 Million

Five Year June,2004            

 

Allocation 2004-05                                        2.500 Million

 

Revised allocation 2004-05                             2.500 Million

 

Releases up to month under report                   2.500 Million

 

Expenditure up to end of month under report      2.500 Million (Committed)

 

Expenditure as % age of allocation (CFY)            (100 %)

 

Expenditure as % age of Releases (CFY)              (16 %)

 

 

REMARKS

 

Repair of Meeri kot is a progress. Also ,an Architect has been engaged by the executing agency for designing the new buildings of Scheme

 

 

Name of scheme:             Construction of Auditorium & Conference

                                                      Hall for Liaquat Memorial Library at

                                                                  Karachi (ADP # 361)

 

Date of approval                                   (29-09-2003)

 

Original Cost                                         19.852 Million

 

Period                                                    (2 Years)

 

 

Expenditure up to end of last                     1.00 Million

Five Year June,2004            

 

Allocation 2004-05                                  2.500 Million

 

Revised allocation 2004-05                       2.500 Million

 

Releases up to month under report             1.250 Million

 

Expenditure up to end of                  2.000 Million (Committed)

  month under report    

 

Expenditure as % age of allocation (CFY)         (10 %)

 

Expenditure as % age of Releases (CFY)          (10 %)

 

Physical progress in CFY up to reporting month  (15 %)

 

 

REMARKS

 

The allocated funds have been released to the Chief Engineer (Buildings) Sindh Hyderabad for execution of civil works as per approved PC-I. The work is in progress.

 

 

Name of scheme:                 Construction of Additional Reading Hall

                                                     for Shamsul Ulema Daudpota Public

                                                       Library at Hyderabad(ADP # 362)

 

Date of approval                                      (29-09-2003)

 

Original Cost                                            4.486 Million

 

Period                                                      (2 Years)

Expenditure up to end of last                      1.00 Million

Five Year June,2004            

 

Allocation 2004-05                                    2.000 Million

 

Revised allocation 2004-05                         2.000 Million

 

Releases up to month under report               2.000 Million

 

 

REMARKS

 

The allocated funds have been released to the Chief Engineer (Buildings) Sindh Hyderabad for execution of civil works as per approved PC-I. The work is in progress.

 

Name of scheme:                    Establishment of Open Air Theatre at

                                                               Larkana (ADP # 364/A)

 

Date of approval                                       (06-01-2004)

 

Original Cost                                             32.198 Million

 

Period                                                        (3 Years)

 

 

Expenditure up to end of last                       0.500 Million

Five Year June,2004            

 

Allocation 2004-05                                     2.000 Million

 

Revised allocation 2004-05                          2.000 Million

 

Releases up to month under report                2.000 Million

 

 

REMARKS

 

The allocated funds have been released to the Chief Engineer (Buildings) Sindh Hyderabad for execution of civil works as per approved PC-I. Drawings of Open Air wer approved and tendering work has been completed by the XEN Buildings.